Before a data centre buys power to bridge a grid delay, price the wait
A data centre waiting for grid power now has another proposal to compare: a package pairing gas generators with batteries.
Full explanation
Trina Storage formally unveiled it in Las Vegas after a September preview. Before paying for a review, ask for the likely grid connection date and the cost of waiting. A named customer, an operating permit and measured fuel savings are three different pieces of evidence. The launch supplies none of them. If a utility cannot supply power when promised, a developer faces two bills: the cost of waiting and the cost of bringing power to the site temporarily. If the grid arrives earlier, the developer has fewer months over which to recover the temporary system’s costs.